China REACH registration and chemical import checks for 2026
China REACH covers new chemical environmental registration. Check IECSC status, the latest MEE rules and separate chemical trade and safety duties.
China REACH is the informal name for China's environmental registration system for new chemical substances. Start with the Inventory of Existing Chemical Substances in China (IECSC), then check the applicable registration rules and separate trade and safety controls. The inventory test appears in MEE's explanation of the new-chemical measures.
An IECSC entry does not establish unrestricted permission to import. Restricted-toxic-chemical trade controls and hazardous-chemical safety duties require separate checks. Use the MEE trade announcement and the Hazardous Chemicals Safety Law.
Before using an old checklist, check the registration-rule changes. A July 2026 MEE notice stopped record-filing from 15 August 2026. MEE's regulations register lists new-chemical registration measures published as Order 40 on 24 October 2026. As of 8 November 2026, that register entry alone is not enough to select a submission route. Obtain the latest operative measures rather than treating historic Order 12 thresholds as a current application guide.
What China REACH registration means
MEE Order 12 established the Measures for the Environmental Management Registration of New Chemical Substances. They took effect on 1 January 2021. This is the historical framework often called "China REACH" or "China new chemical notification." Its text required registration before manufacture or import. It also included ongoing risk-management, information-transfer and reporting duties. See the Order 12 text in the State Council Gazette.
REACH in China needs its own inventory check. Do not use an EU REACH registration as evidence that the China REACH regulation is satisfied. Establish the substance's Chinese inventory status and applicable Chinese permissions using the Chinese measures. Keep that assessment separate from any EU compliance file.
The same care applies to product exclusions. Under Order 12, a finished product exclusion did not necessarily cover its raw materials or intermediates. New substances diverted to other industrial uses could also remain covered. A cosmetics, pharmaceutical or pesticide use was therefore not a blanket exemption for every substance in that supply chain. Check the activity and substance against the scope provisions, then confirm the latest applicable text.
Check substance identity and IECSC status first
Build the screening file before choosing a registration category. Ask the supplier and Chinese importer to assemble:
- The substance name and identity information used for the inventory search.
- Expected annual manufacture or import volume in China.
- The intended industrial use and identity of the importer or manufacturer.
- Formulation details needed to assess ingredients separately.
- Polymer information where a polymer-related route is being considered.
Treat this as preparation for an assessment, not proof of eligibility. Record what was searched, which source was used and the basis for the identity match. Don't treat a supplier's statement that a product is "China REACH compliant" as the screening record.
Under Order 12, the legal test for a new substance was whether it appeared in IECSC. But listed substances subject to new-use management required further assessment for industrial uses outside the permitted uses. MEE's official explanation describes that distinction.
For a listed substance, check any use conditions before closing the inventory assessment. For an unlisted substance, take the identity, volume and use information into the latest MEE registration assessment. Keep an unresolved identity match open rather than turning it into a conclusion that registration is unnecessary.
Why an old China REACH filing checklist is unsafe
Order 12's historical annual-volume bands were regular registration at 10 tonnes or more, and simplified registration from 1 to below 10 tonnes. Record-filing covered quantities below 1 tonne and qualifying polymer cases. These were the Order 12 baseline rules, not a current route-selection table.
The Order 12 polymer conditions were specific. They included new monomer or reactant content not exceeding 2%, or low-concern polymer status. "Polymer" alone did not establish an exemption under that text. The name is not enough. Preserve the evidence for any claimed condition instead of treating the product description as sufficient.
MEE's notice signed 31 July 2026, 环办固体函〔2026〕301号, changed the handling of filing cases. It stated that new-chemical environmental record-filing would stop from 15 August 2026. This did not stop every registration application. See the official notice.
For cases meeting Order 12 Article 10(3), the July notice required an application before production or import. The package included an application form and evidence of the qualifying condition. It also required already-held environmental and health hazard information and environmental-risk information. MEE was to accept and approve those applications by reference to simplified-registration procedures and time limits.
The notice also said it would expire automatically when new provisions were issued. Order 40's register listing does not set out registration categories, applicant requirements or transition provisions. Before submitting, obtain the latest operative text and check those points.
An old filing checklist cannot establish the route. Filing may no longer be open, and a quantity below 10 tonnes does not lock in one permanent procedure.
Separate the three chemical compliance checks
China chemical regulations use different inventories and lists for different purposes. Keep separate results for each check rather than recording one general "approved" status.
| Check | Question to resolve | Official starting point |
|---|---|---|
| New-chemical environmental registration | What does IECSC status mean for the intended activity and use? | Latest MEE measures |
| Restricted-toxic-chemical trade control | Does the shipment fall within a listed entry and its conditions? | 2023 trade announcement |
| Hazardous-chemical safety | Which safety documentation and hazardous-chemical registration duties apply? | Hazardous Chemicals Safety Law |
For covered imports or exports, the restricted-toxic-chemical announcement requires an application to MEE for an environmental-management release notice. That notice is used for customs formalities. Read the entry conditions and annex before deciding whether a transaction is permitted. A release notice is distinct from new-substance registration, and the list is not blanket permission to trade each named chemical.
The 2023 announcement replaced the preceding 2020-list announcement. Check for later changes before relying on a saved copy or an old permitted-use window.
Check hazardous-chemical documentation separately
The Hazardous Chemicals Safety Law took effect on 1 May 2026. Article 31 requires hazardous-chemical producers and importers to provide a matching Chinese safety data sheet and Chinese chemical safety label that meet national standards. Article 86 requires hazardous-chemical registration with the responsible body under the emergency-management authority. See the law's official text.
This registration is separate from MEE new-substance registration. Article 89 directs new-chemical environmental registration to the relevant environmental laws, administrative regulations and rules. Passing one assessment does not close the other.
For the China Catalogue of Hazardous Chemicals, check the catalogue together with applicable updates. Use the Ministry of Emergency Management's announcement index to locate official updates. For China GHS regulations, confirm the applicable national standards rather than assuming an existing foreign SDS and label meet the Hazardous Chemicals Safety Law.
Before committing to an import
Ask the importer to retain the inventory assessment, applicable current rules and evidence supporting the selected route. Check the restricted-toxic-list annex against the intended transaction. Confirm who will handle any required permissions and Chinese safety documentation before agreeing shipment timing.
Where the team relies on an existing certificate, ask how it covers the planned activity and use. Confirm its treatment under the latest provisions rather than assuming older arrangements continue unchanged.
If your task is importing chemicals from China into another country, assess the destination country's rules separately. A Chinese export assessment does not replace that review.
RegAffairs AI's answer on China REACH explains the distinct screening checks.