When must contaminated land be reported in NSW?

In NSW, under section 60 of the Contaminated Land Management Act 1997 (CLM Act), you must notify the EPA as soon as practicable after you become aware of the contamination. The duty falls on anyone whose activities have contaminated land, and on the owner of contaminated land. You count as aware if you ought reasonably to have been aware. It only applies once one of the triggers set out in the EPA's section 105 guidelines is met. (The guidelines say "as soon as practical"; the EPA summary says "as soon as practicable".)

Approach: My datasets hold only the NSW EPA list of notified and regulated sites, not the Act, so I read the EPA's Guidelines on the Duty to Report Contamination under the CLM Act (2015 edition, which revokes the July 2015 edition). I couldn't open the current Act on the NSW legislation site, so the section 60 wording below comes from the guidelines and the EPA summary, not the Act itself.

What triggers the duty (Guidelines s2.1, citing s60(3)) You must notify if any of these is met:

  1. On-site soil (s60(3)(b)): the contaminant is at or above a level in Schedule B1 of the NEPM (Assessment of Site Contamination) 1999 (NEPC 2013), or another approved guideline value, for the current or approved land use, and people have been or foreseeably will be exposed. In practice this means either:
    • the 95% upper confidence limit of the average concentration is equal to or above the Health Investigation Level or Health Screening Level; or
    • any single sample is equal to or more than 250% of that level.
  2. A criterion set by the regulations: at publication, the Contaminated Land Management Regulation 2013 set none.
  3. Off-site or water migration (s60(3)(a)): the contaminant or a by-product has entered, or will foreseeably enter, neighbouring land, the atmosphere, groundwater or surface water. It must also be, or foreseeably be, above the NEPM levels and stay at or above them.

Specific triggers (Guidelines s2.3)

  • Neighbouring land: the 95% upper confidence limit is above the HIL/HSL, or a single sample is more than 250% of it, and it will foreseeably stay above. This also applies where contamination will foreseeably reach neighbouring land.
  • Asbestos: friable asbestos at or above 0.001% w/w in a single soil sample, and exposure to airborne fibres at or above 0.01 fibres/mL. Bonded "fibro" and naturally occurring asbestos are excluded.
  • Groundwater or surface water: concentrations above the NEPM groundwater investigation level that will foreseeably persist. Separate-phase liquid (an immiscible organic liquid) must be notified regardless of concentration, except in the scenarios in s2.6.3.
  • Vapour intrusion: soil, soil-vapour or groundwater results at or above the NEPM vapour levels, persisting, with actual or foreseeable exposure.
  • Explosive or acutely toxic ground gas: gas in buildings or underground services above 25% of the lower explosive limit, or 25% of the acute toxicity, needs immediate action including notification. This doesn't apply if approved gas controls are in place.
  • Unsampled pathways: if relevant media haven't been sampled, you should assume contaminants move above the trigger levels, unless the amounts released are negligible. Uncertainty "should not be used as reasons to delay reporting."

When the duty is not intended to apply (Guidelines s2.5)

  • Widespread diffuse urban pollution not linked to a specific activity.
  • On-site-only contamination that is unlikely to migrate, where the site has been assessed as suitable for its proposed use under the Environmental Planning and Assessment Act 1979.
  • Levels at or below ambient background.
  • Illegal dumping, and waste stockpiles covered by the Protection of the Environment Operations Act 1997 (POEO Act).
  • Sites already notified with no change in circumstances.
  • Sites under a Part 3 declaration, order or proposal, or formerly declared with no contaminating activity since.
  • Sites with a site audit statement for the current use, no contaminating activity since and no off-site impacts.

The EPA may still regulate any of these.

When you are taken to be aware (Guidelines s2.6, s60(9)(b)) The EPA looks at your experience, qualifications and training, whether you could reasonably have sought advice, and the circumstances. If you run potentially contaminating activities, or develop land with that history, you "should seek advice." The guidelines give 12 worked examples. For instance, Example 12 is an industrial site with phase-separated hydrocarbons, an unclear plume and unknown groundwater concentrations: duty to report.

How to report and penalties (Guidelines s2.7–2.8)

  • Notification must be on the EPA-approved form, with supporting reports such as consultant reports attached.
  • The guidelines give maximum penalties for not reporting of $1,000,000 plus $77,000 per day for a corporation, and $250,000 plus $33,000 per day for an individual. I couldn't check these against the current Act.
  • Anyone can report suspected contamination on Environment Line, 131 555.

The CLM Act duty is separate from other reporting duties. Pollution incidents that cause or threaten material harm must also be reported under s148 of the POEO Act.

Sources:

Q.02

How does EPA regulation differ from planning approval?

In NSW, the EPA regulates land under the Contaminated Land Management Act 1997 (CLM Act) only when the contamination is "significantly contaminated", meaning it is significant enough to warrant regulation. Planning authorities (usually councils, or the Department of Planning) deal with all other contaminated land through rezoning and development consent under the Environmental Planning and Assessment Act 1979 (EP&A Act). The EPA's tool is direct orders against responsible parties. The planning system's tool is that land must be suitable for its proposed use before development can go ahead.

Approach: I checked the NSW EPA list of notified and regulated sites (14 July 2026 edition) for how sites are split between the two pathways. I then read the EPA's pages on its own role and on the role of planning authorities, and the background notes to the published list. I did not read the Acts or the SEPP themselves, so section numbers below are as the EPA pages give them.

EPA regulation (CLM Act)Planning approval (EP&A Act)
Which landLand the EPA declares "significantly contaminated land"Land that is not "significantly contaminated" and poses no unacceptable risk under its current, approved use
What triggers itA section 60 notification (or other information), then an EPA assessment against the section 12 factors. These include harm already caused; whether substances are toxic, persistent or bioaccumulative; exposure pathways; current and approved uses of the land and adjoining land; and migration off the landA rezoning or development application. The authority "must consider" whether contamination makes the site unsuitable for the proposed use. If it does, the land "must be remediated before it can be developed"
Who actsThe EPA directs responsible parties. As far as practicable it orders, in this sequence, those responsible for the contamination, then the landowner, then the notional owner (for example financiers)The consent authority, typically a local council or the Department of Planning, sets conditions on the development
InstrumentsPreliminary investigation orders; clean-up and prevention notices under s46 (these can be issued before or after a declaration, and can require immediate action); voluntary management proposals; management orders; ongoing maintenance orders; cost recovery and financial assuranceThe EP&A Act, the State Environmental Planning Policy (Resilience and Hazards) 2021 and the Managing Land Contamination: Planning Guidelines
RemediationRequired by order or by an approved proposal, on the EPA's timetableThe SEPP makes remediation permissible, defines when consent is required, requires all remediation to comply with standards, and requires councils to be notified of all remediation proposals
TimingCan happen regardless of whether any development is plannedTied to redevelopment. The EPA says such sites "may still need to be remediated, but can be done with any building or redevelopment"
Public recordDeclaration published in the NSW Government Gazette and the EPA's Record of NoticesShown on section 10.7 planning certificates issued by the council

How the two connect

  • Every notification starts with the EPA. It first checks whether the report is really a pollution incident, which is handled under the POEO Act instead. The EPA says that "in most cases" the contamination is not a significant risk, so the site goes to planning. It then informs the council "so that the information can be considered at the right time."

  • A site can be significant and still go through planning. The list has a "managed via the planning process (EP&A Act)" class. It covers sites the EPA found "significant enough to warrant regulation" but left to the consent authority, "with EPA involvement as necessary."

    • In the July 2026 list I found 10 sites in this class, for example Former AGL Gasworks, Millers Point [1] and Former Mascot Galvanising [2].
    • Another 5 are listed as "addressed via the planning process", for example the Cross City Tunnel, Darlinghurst [3].
    • By comparison, sites such as Orica Botany are listed as "currently regulated under CLM Act" [4].
  • CLM Act status shows up on planning certificates. Section 10.7(2) certificates "must record" whether the land is:

    • declared significantly contaminated;
    • under a management order;
    • under an approved voluntary management proposal;
    • under an ongoing maintenance order; or
    • the subject of a site audit statement.

    These are the s59(2)(a)–(e) matters. Councils "may" add other contamination information on s10.7(5) certificates.

  • Being on the EPA list is not the same as being regulated. The EPA says inclusion "does not necessarily mean the contamination is significant enough to regulate under the CLM Act."

In practice, a planning consent does not take away the EPA's CLM Act powers. Equally, the duty to report under s60, covered in your previous question, applies whichever pathway the site ends up in.

Sources:

Q.03